Creating and Recommending Baselines in a UCM Project is done
through the ClearCase Project Explorer.
The Project Explorer can be started through the Start menu in Windows or
through the ClearCase Explorer on the UCM page of the Toolbox tab.
Creating a new
Baseline:
Select the integration stream of the UCM Project where the
new baseline is to be created. Then
right click on the integration stream and select Make Baseline… This will
bring up the Make Baseline Wizard.
In the Base Name box enter the name of the
baseline you are creating. This should
be descriptive but concise. Make sure
baseline naming conventions are followed. Enter a description of the baseline in the Description
box. If the new baseline is to be used within the current UCM
Project, leave Baseline Type to Incremental. If the baseline is to be used outside of the
current UCM Project, set this to Full.
Select the Activities tab.The Activities tab will show all the activities on the
integration stream that have not been included in a baseline. Select the activities to include in the new
baseline.
Care must be taken to make sure the activities selected do
not have dependencies on other activities that have not been selected. In this example, the second activity has been
selected with out the first activity.
The same file was changed in both activities and an earlier version the
file is in the activity that was not selected.
This causes a dependency between the two activities. If this happens, the following dialog will be
displayed.
If this dialog is displayed, select OK and select the activity that has caused the dependency from the
Activity tab. Once all activities have been selected for the new baseline,
select the OK button. This will create the new baseline.Close all windows.
Recommending a
Baseline:
To recommend a baseline for a UCM Project, right mouse the
integration stream of the UCM Project and select Recommend Baselines… This
will bring up the Recommend Baseline window.
Highlight the component that contains the new baseline to be
recommended and select Add…
In the Add Baseline window, select the baseline of the
component and then select the OK button.
Repeat this process for any other component baselines that
need to be up modified.
Note: When a new
baseline is created it may affect more then one component. Be sure to update
all the components that were affected by the new baseline.
Once all components have been updated, select OK.
This will create a new recommended baseline for the UCM Project.